Strict factory test ensures every piston refrigeration compressor works stably after delivery. Standardized inspection procedure detects defects before shipment and reduces on-site failure risk for cold storage projects.
Visual inspection is the first step. Inspect casting surface, welding seam, nameplate marking and pipe interface to check for sand holes, crack or dimension deviation.
Performance test includes 2-hour continuous running under rated working condition. Testers record pressure, temperature, motor current, vibration and noise data during the whole test period.
Leakage test applies nitrogen pressure holding test. Maintain pressure for specified time, any pressure drop beyond threshold means leakage defect and the compressor will be rejected.
Electrical safety test covers motor winding insulation resistance and protection function simulation. Phase loss, over-current and high-pressure protection functions are verified one by one.
After passing all tests, compressors are cleaned, dried and sealed. Blind flanges are fitted on suction and discharge ports to prevent foreign matter entering the cavity.
xtldcool piston refrigeration compressor factory implements full inspection for each unit. Test reports are attached to compressor shipment documents for customer reference.
Random sampling audit will be carried out periodically. The audit checks finished product quality to guarantee consistency of batch production.
FAQ
Q: What is the duration of rated working condition running test in factory? A: 2 hours continuous operation performance test.
Q: What medium is used for compressor factory leakage pressure test? A: Nitrogen gas for pressure holding leakage inspection.
Q: What items are included in electrical safety test? A: Motor insulation test and protection function simulation test.
Q: How to protect compressor internal cavity after factory inspection? A: Seal suction and discharge ports with blind flanges.
Q: What document will be delivered together with compressor? A: Factory performance test report of the unit.
Q: Does xtldcool test every piston compressor before shipment? A: Yes, every single compressor undergoes complete factory inspection.
Q: What purpose of periodic random sampling audit? A: Keep stable batch product quality consistency.
Keywords embedded: piston refrigeration compressor, cold storage piston compressor, semi-hermetic piston compressor, cold storage refrigeration compressor, piston refrigeration compressor factory, industrial piston refrigeration compressor, piston compression unit, low-temperature cold storage piston compressor, piston refrigeration compressor OEM, piston refrigeration compressor export manufacturer
Quality Inspection Standards for Piston Refrigeration Compressor Before Factory Shipment Strict factory test ensures every piston refrigeration compressor works stably after delivery. Standardized inspection procedure detects defects before shipment and reduces on-site failure risk for cold storage projects.
Visual inspection is the first step. Inspect casting surface, welding seam, nameplate marking and pipe interface to check for sand holes, crack or dimension deviation.
Performance test includes 2-hour continuous running under rated working condition. Testers record pressure, temperature, motor current, vibration and noise data during the whole test period.
Leakage test applies nitrogen pressure holding test. Maintain pressure for specified time, any pressure drop beyond threshold means leakage defect and the compressor will be rejected.
Electrical safety test covers motor winding insulation resistance and protection function simulation. Phase loss, over-current and high-pressure protection functions are verified one by one.
After passing all tests, compressors are cleaned, dried and sealed. Blind flanges are fitted on suction and discharge ports to prevent foreign matter entering the cavity.
xtldcool piston refrigeration compressor factory implements full inspection for each unit. Test reports are attached to compressor shipment documents for customer reference.
Random sampling audit will be carried out periodically. The audit checks finished product quality to guarantee consistency of batch production.
FAQ
- Q: What is the duration of rated working condition running test in factory? A: 2 hours continuous operation performance test.
- Q: What medium is used for compressor factory leakage pressure test? A: Nitrogen gas for pressure holding leakage inspection.
- Q: What items are included in electrical safety test? A: Motor insulation test and protection function simulation test.
- Q: How to protect compressor internal cavity after factory inspection? A: Seal suction and discharge ports with blind flanges.
- Q: What document will be delivered together with compressor? A: Factory performance test report of the unit.
- Q: Does xtldcool test every piston compressor before shipment? A: Yes, every single compressor undergoes complete factory inspection.
- Q: What purpose of periodic random sampling audit? A: Keep stable batch product quality consistency.
Keywords embedded: piston refrigeration compressor, cold storage piston compressor, semi-hermetic piston compressor, cold storage refrigeration compressor, piston refrigeration compressor factory, industrial piston refrigeration compressor, piston compression unit, low-temperature cold storage piston compressor, piston refrigeration compressor OEM, piston refrigeration compressor export manufacturer